Road Project Update: Road edge shouldering and lane striping have been completed on Kiel and Townhall Rds.   Final stage of the project will wrap up within the next few weeks with ditch shaping on St Paul Rd and the installation of two (2) replacement culverts on Townhall Rd in areas not paved in 2020.

TEST TW WEATHER

Road Project Update

Road surface pulverizing and final grading will be completed on Thu 9/17.  The picture taken from W1097 Kiel Rd shows the full road width after final grading.  
 
The double culvert visible on the left was installed to channel westbound stormwater flows that previously backed up at the bottom of the hill causing stormwater to flow over Kiel Rd and flood crops on the south side of the roadway.
 
Paving of 5+ miles of Town of Calumet road surfaces will begin Friday, 9/18, weather permitting.
 
Paving is expected to last from 5 to 10 business days.