Open Book:

TEST TW WEATHER

Town of Calumet Road update.

Roadside ditch reshaping has been completed on Kiel, Townhall and St Paul Rds.  This activity is coupled with previous culvert replacements to direct stormwater away from roadway surfaces and manage flow volumes through the roadside culvert system.
 
Upcoming activity includes roadway pulverizing on Kiel and Townhall Rds beginning Thu 9/3/20.  Next will be final roadway grading followed by asphalt paving on Kiel and Townhall Rds beginning, weather permitting, on Mon 9/14.
 
Final stage of the 2020 project will be paving of 20+ road edge patches located on Schoenborn, St Paul and Schumacher Rds.  This activity is expected to start between Mon 9/28 and Mon 10/4.