Road Project Update: Road surface pulverizing and final grading will be completed on Thu 9/17.  The picture taken from W1097 Kiel Rd shows the full road width after final grading.     The double culvert visible on the left was installed to channel westbound stormwater flows that previously backed up at the bottom of the hill causing stormwater to flow over Kiel Rd and flood crops on the south side of the roadway.   Paving of 5+ miles of Town of Calumet road surfaces will begin Friday, 9/18, weather permitting.   Paving is expected to last from 5 to 10 business days.

TEST TW WEATHER

Town of Calumet Road update.

Roadside ditch reshaping has been completed on Kiel, Townhall and St Paul Rds.  This activity is coupled with previous culvert replacements to direct stormwater away from roadway surfaces and manage flow volumes through the roadside culvert system.
 
Upcoming activity includes roadway pulverizing on Kiel and Townhall Rds beginning Thu 9/3/20.  Next will be final roadway grading followed by asphalt paving on Kiel and Townhall Rds beginning, weather permitting, on Mon 9/14.
 
Final stage of the 2020 project will be paving of 20+ road edge patches located on Schoenborn, St Paul and Schumacher Rds.  This activity is expected to start between Mon 9/28 and Mon 10/4.