Road Project Update: Road surface pulverizing and final grading will be completed on Thu 9/17.  The picture taken from W1097 Kiel Rd shows the full road width after final grading.     The double culvert visible on the left was installed to channel westbound stormwater flows that previously backed up at the bottom of the hill causing stormwater to flow over Kiel Rd and flood crops on the south side of the roadway.   Paving of 5+ miles of Town of Calumet road surfaces will begin Friday, 9/18, weather permitting.   Paving is expected to last from 5 to 10 business days.

TEST TW WEATHER

The “lift” of the road surface on Kiel Rd through the marsh (between Townhall & Schoenborn Rds) has been completed. This activity raised the road surface as much as 30 inches in some sections. The road is open to traffic at reduced speeds. Caution is advised. Paving in this area will begin in September.

The next stage of Our Town of Calumet’s 2020 Road Construction has begun.  This stage involves replacement of failed stormwater culverts under Kiel & Townhall Rds. Improvement is also being made to several sections of roadside ditches enabling stormwater to properly flow away from road surfaces.  Paving in these areas on Kiel Rd will begin in September.